August 2025 to 2028
This multi-year project includes the full closure of Columbus Road from Country Lane to Cedarbrook Trail to support area growth. North/south routes crossing Columbus will remain open. Detour routes will be in place for the duration of the work.
July 2025
Work includes the installation of pedestrian crossovers complete with signage, pave markings, flashing beacons, audible pedestrian push buttons, and concrete sidewalk connections.
Now through August 2025
Work includes the removal of base and top asphalt, curb and sidewalk repairs, new base and top asphalt, driveway and sod restoration.
July 2025 to September 2025
Work includes repairing the concrete culvert located under Columbus Road, east of Garrard Road and installing a new guide rail system.
July 2025 to December 2025
Work includes the replacement of White Bridge on Columbus Road West over Lynde Creek. The bridge is being widened to accommodate bike lanes and sidewalks. The project also includes creek re-alignment and landscaping.
July 2025 to December 2025
Work includes repairs on the existing concrete beams and the installation of a rock embankment along the south bridge footing.
It's important to know that not all construction projects happening in Whitby are being run by the Town. Some projects are being run by Bell, Rogers, developers, Durham Region, and more.
Stay informed on Region of Durham construction projects happening in Whitby.
Please note that we may not have details on all projects happening in Whitby, but we will keep you informed about the projects the Town is working on. Don't forget to subscribe to the Construction Updates news category to stay in the loop.
Contact Us