August 2025 to 2028
Work will take about three years and requires coordination with multiple agencies and utilities. Detour routes will be posted, but all north/south roads crossing Columbus Road will remain open. This project supports growth in Brooklin and Whitby.
Starting August 2025, hydro poles will be relocated to the south side of Columbus Road to allow widening from 2 to 5 lanes (even more at intersections). This 2.2 km relocation is the first step and should wrap up by late 2025.
Next, trees and brush will be cleared in late 2025 to early 2026, following environmental rules. This must be done by April 1, 2026. Bell and other utilities will also adjust their infrastructure. Major road construction begins in 2026, including new water crossings and water/sewer line installation.
June 2025 to August 2025
Work includes a four-week closure of the Whitby Waterfront Trail through Shirley Scott Park (at Front and Brock Streets). A small section of trail through the park is closed to the public to support the construction of a new pop-up visitor centre. Trail users can still access the waterfront trail along Front Street, reconnecting on Brock Street. This project is funded through a federal Tourism Growth Program Grant.
June 2025 to August 2025
Work includes the installation of pedestrian crossovers complete with signage, pave markings, flashing beacons, audible pedestrian push buttons, and concrete sidewalk connections.
June 2025 to August 2025
Work includes the removal of base and top asphalt, curb and sidewalk repairs, new base and top asphalt, driveway and sod restoration.
July 2025 to September 2025
Work includes repairing the concrete culvert located under Columbus Road, east of Garrard Road and installing a new guide rail system.
July 2025 to December 2025
Work includes the replacement of White Bridge on Columbus Road West over Lynde Creek. The bridge is being widened to accommodate bike lanes and sidewalks. The project also includes creek re-alignment and landscaping.
July 2025 to December 2025
Work includes repairs on the existing concrete beams and the installation of a rock embankment along the south bridge footing.
It's important to know that not all construction projects happening in Whitby are being run by the Town. Some projects are being run by Bell, Rogers, developers, Durham Region, and more.
Stay informed on Region of Durham construction projects happening in Whitby.
Please note that we may not have details on all projects happening in Whitby, but we will keep you informed about the projects the Town is working on. Don't forget to subscribe to the Construction Updates news category to stay in the loop.
Contact Us