Roads

Project Number: T-10-2017
Price and Way Street Reconstruction – Under construction from August 28, 2017 to December 17, 2017.
Road base, storm sewer, curb and gutter, sidewalk and base asphalt.

Project Number: T-9-2017
King Street Reconstruction – Under construction from September 4, 2017 to December 22, 2017.
New watermain, sanitary sewer, storm sewer, curb and gutter, sidewalk and base asphalt.

Project Number: T-7-2017
Street Light Installation – Under construction from October 16, 2017 to December 17, 2017.
Anderson Street (Promenade Drive to Conlin Road), Conlin Road (Anderson Street to East Town Limit), Thickson Road (Taunton Road to Gateway Court) and Dundas Street (East to West Town Limits) – Street light LED replacement.

Project Number: T-11-2017
Downtown Sidewalk and Boulevard – Under Construction from October 30, 2017 to December 8, 2017.
Dundas Street (Brock Street to Hickory Street) – Sidewalk replacement and pressed concrete boulevard.

Region of Durham Whitby Projects

Victoria Street Widening – Halls Road to Seaboard Gate –Under construction until August 2018.

Ministry of Transportation Projects

Henry Street Bridge Replacement – bridge reopened in November 2017.